UN ECE Regulation 10 requires EMC tests for vehicles used for automotive. According to UN ECE R10 revision 6, vehicles are grouped into two:
- Vehicles in configuration other than ”REESS charging mode coupled to the power grid”
- Vehicles in configuration “REESS charging mode coupled to the power grid”
On this post we will list all EMC tests for vehicles in configuration ”REESS charging mode coupled to the power grid”
Test under UN ECE R10 Rev.6 |
Vehicles in configuration (vehicles without immunity-related functions) |
Vehicles in configuration (vehicles with immunity-related functions) |
Test Site |
Radiated Emissions (30MHz-1GHz) Broadband (Peak and Quasi-Peak) |
Required | Required | ALSE or OTS |
Radiated Emissions (30MHz-1GHz) Narrowband (Average) |
Not Required | Not Required | ALSE or OTS |
Conducted Emissions (0.15-30MHz) for AC/DC power lines |
Required | Required | ALSE, OTS or Shielded Enclosure |
Conducted Emissions (0.15-30MHz) for wired network ports |
Required | Required | ALSE, OTS or Shielded Enclosure |
Harmonics Emissions (AC power lines) ≤ 16 A per phase (IEC 61000-3-2) > 16 A and ≤ 75 A per phase (IEC 61000-3-12) |
Required | Required | N/A |
Voltage fluctuations and Flicker Emissions (AC power lines) ≤ 16 A per phase (IEC 61000-3-3) > 16 A and ≤ 75 A per phase (IEC 61000-3-11) |
Required | Required | N/A |
Radiated Immunity (ISO 11451-2)* 20MHz-2GHz |
Not Required | Required |
-ALSE or OTS -Dynamometer or insulated axle |
EFT/Burst Immunity (IEC 61000-4-4) AC or DC power lines: ± 2 kV |
Not Required | Required | Reference Ground Plane |
Surge Immunity (IEC 61000-4-5) AC power lines: ± 2 kV DC power lines: ± 0.5 kV |
Not Required | Required | Reference Ground Plane |
* If vehicle is longer than 12 m and/or wider than 2.60 m and/or higher than 4.00 m, Bulk Current Injection (BCI) tests shall be applied according to ISO 11451-4 standard. In this case, current level is 50mA rms.
Required tests are for vehicle
What are immunity related functions?
EMC tests for Vehicles in configuration other than ”REESS charging mode coupled to the power grid”
Do you need more information about ECE R10 Tests and Certification?
Download our ECE R10 Certification Guide and learn more about ECE R10 tests and certification. Guide covers for both ESAs and vehicles.